Fixed
Shocking repair attempt
Reported via iOS in the Potholes / Highway Condition category anonymously at 11:27, Wednesday 24 June 2026
Sent to North Northamptonshire Council less than a minute later. ref: 9675403.
You have the nerve to say this is repaired you have close my ticket saying completed. This is appalling, you have left the hole on the other side, you have failed to do a proper repair and seal it so it will soon be gravel across the road again. This is an appalling waste of tax payers money. Do better and fill this hole in correctly
Updates
-
If you believe that your concerns are an emergency (such as flooding, dangerous potholes/carriageway defects, highway obstructions, fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 11:27, Wednesday 24 June 2026
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 11:27, Wednesday 24 June 2026
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 28 days. Please be assured that you will receive an update once repairs are concluded.
Posted by North Northamptonshire Council at 08:18, Tuesday 7 July 2026
-
Still open, via questionnaire, 09:54, Monday 27 July 2026
-
Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled
Posted by North Northamptonshire Council at 09:58, Thursday 30 July 2026
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 07:47, Friday 31 July 2026
-
Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled
State changed to: Investigating
Posted by North Northamptonshire Council at 07:57, Friday 31 July 2026
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 12:17, Friday 31 July 2026
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by North Northamptonshire Council at 09:43, Tuesday 4 August 2026
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by North Northamptonshire Council at 11:03, Tuesday 4 August 2026
-
You came back and did a bit to the left bit the poor gravel infill that you originally did (the white area) has breakdown started to break down again.
State changed to: Open
Posted anonymously at 16:08, Wednesday 2 September 2026
Still open, via questionnaire -
Investigation: Completed (Defect Found), Defect Repair: Work Completed - Thank you for your enquiry. We can confirm that we have been made aware of this issue and a works order has been raised on a routine safety inspection. These works are due to be completed by 06/10/2026 Please be assured that you will receive an update once repairs are concluded.
State changed to: Fixed
Posted by North Northamptonshire Council at 15:47, Tuesday 8 September 2026
This report is now closed to updates from the public. You can make a new report in the same location.