Multiple pot holes, crumbling verges and ruts caused by hgv's
Reported via desktop in the Potholes / Highway Condition category anonymously at 12:30, Thursday 19 February 2026
Sent to North Northamptonshire Council less than a minute later. ref: 8954629.
This whole road is unsafe. there are dozens of pot hole, the drain at the top of the road floods the road and causes a stream to travel down the road. the road has big ruts in places, caused by lorries - in the winter, this caused my car to skid and i ended up in a ditch, with a repair costing over £600.
Although a back road, this is the main route for several businesses and the state of this road is awful - I actually dread using it every day.
Someone needs to come out and view this whole stretch and do an assessment on it, as the issues raised on the map do not show the full extent of the issues.
Updates
-
If you believe that your concerns are an emergency (such as flooding, dangerous potholes/carriageway defects, highway obstructions, fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 12:30, Thursday 19 February 2026
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 12:30, Thursday 19 February 2026
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 7 days. Please be assured that you will receive an update once repairs are concluded.
Posted by North Northamptonshire Council at 14:15, Thursday 26 February 2026
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 13:26, Monday 2 March 2026
-
Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled
State changed to: Investigating
Posted by North Northamptonshire Council at 15:11, Wednesday 4 March 2026
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 06:17, Thursday 5 March 2026
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by North Northamptonshire Council at 09:39, Thursday 5 March 2026
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by North Northamptonshire Council at 13:38, Thursday 5 March 2026
-
Majority of pot holes filled.
Ruts in the road are still present and still dangerous.
State changed to: Open
Posted anonymously at 20:18, Thursday 19 March 2026
Still open, via questionnaire