Closed
Worsening hole near centreline heading north past 'uneven road' sign
Reported via desktop in the Potholes / Highway Condition category anonymously at 15:02, Tuesday 17 February 2026
Sent to North Northamptonshire Council less than a minute later. ref: 8940530.
Entirely foreseeably, instead of being repaired as it warranted on any rational assessment of risk, in the time since this fault was logged and scheduled to be addressed 'within 180 days' (i.e. 6 months in language that does not seek to obscure the woeful response time), the defect is worsening by the day and is now unacceptably severe.
In combination with the additional one on the nearside about 80m further north, there is now a really nasty game of chicane roulette to play in face of oncoming traffic, especially at night time in the wet, if you don't fancy risking a visit to the tyre depot/garage, or even the casualty department by tangling with this on a motorcycle.
Of course, if a vehicle suffers a catastrophic tyre or suspension failure as a result of impacting this trench, any loss of control taking the vehicle to the off-side will likely result in a head-on.
Given the exponential increase in HGV traffic on this road due to the many bonkers logistics park planning approvals recently, the last thing any other road user venturing along the A6116 needs now is the perpetuation of entirely and properly repairable defects until they become truly life threatening.
Get a grip and fix it please, before some poor soul comes to grief!
Updates
-
If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 15:02, Tuesday 17 February 2026
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 15:02, Tuesday 17 February 2026
-
Investigation: Completed (Scheduled Maintenance) - Pre-patching works is scheduled to be completed in this area on 17th March 2026 for 10 nights to carry out repairs to identified defects across the section of road. This programme enables us to address multiple issues efficiently in preparation for surface dressing.
If you are aware of any additional defects not covered by this report, or if you believe the issue you reported has not been addressed, please submit a new enquiry and, where possible, include a What3Words location, photographs, and nearby landmarks to help us locate and assess the concern quickly.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysState changed to: Closed
Posted by North Northamptonshire Council at 13:42, Thursday 12 March 2026
This report is now closed to updates from the public. You can make a new report in the same location.