Investigating
Unfinished Repairs
Reported via desktop in the Pothole / Failed Reinstatement category anonymously at 14:26, Tuesday 27 January 2026
Sent to North Northamptonshire Council less than a minute later. ref: 8779294.
Last August, work was begun to patch holes at the top of Wood Street in Geddington. However, the patches were below mud and water levels which soon filled with both. Also repairs were made to the path leading to the Brickyard Garden and the Chase, (a frequently used path for vehicles, horses, bikes and walkers, some at night) but only 10 feet were completed. A further section was dragged, presumably in preparation for further asphalt, but leaving the road in worse condition. The dragging also lowered the road surface below surrounding area meaning it floods more frequently. As the surrounding fields belong to the Boughton Estate, requests were made to them, but they insist it is the responsibility of the Council. Our mandate requires the Geddington Brickyard Garden CIC to be open 24/7 and that is clearly not possible now. Can you send someone to make an assessment and contact the Brickyard before someone is injured?
Updates
-
If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 14:26, Tuesday 27 January 2026
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 14:26, Tuesday 27 January 2026
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 180 days (26 weeks), however we are currently operating for completion to be within 90 days. Please be assured that you will receive an update once repairs are concluded.
Posted by North Northamptonshire Council at 13:51, Tuesday 3 February 2026
-
Main roblems ar after rain, because the road is lower than the surrounding fields now, and of course, the potholes can't be seen
Posted anonymously at 15:38, Sunday 8 March 2026
Still open, via questionnaire -
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 180 days (26 weeks), however we are currently operating for completion to be within 90 days. Please be assured that you will receive an update once repairs are concluded.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by North Northamptonshire Council at 08:59, Monday 9 March 2026
-
As I mentioned in the last questionaire, part of the problem is the last work lowered the road below the verges, though the fields surrounding the road are lower. If a few places on the side of the road could be dug out, the road would drain, make the potholes more visible, and be less hazardous for bikes, horses and pedestrians who regularly use it
Posted anonymously at 16:55, Saturday 25 April 2026
Still open, via questionnaire -
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 180 days (26 weeks), however we are currently operating for completion to be within 90 days. Please be assured that you will receive an update once repairs are concluded.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by North Northamptonshire Council at 10:47, Tuesday 28 April 2026
-
Still open, via questionnaire, 16:30, Friday 29 May 2026
-
Still open, via questionnaire, 18:56, Friday 26 June 2026
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 12:04, Friday 3 July 2026
-
Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled
State changed to: Investigating
Posted by North Northamptonshire Council at 14:19, Tuesday 7 July 2026