Investigating
Drain in gutter completely blocked
Reported via iOS in the Blocked/Damaged category anonymously at 09:49, Sun 23 November 2025
Sent to North Northamptonshire Council less than a minute later. ref: 8453155.
Drain at junction of Headlands and Glebe Ave completely blocked and floods Headlands every time it rains.
Updates
-
If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 09:49, Sun 23 November 2025
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 09:49, Sun 23 November 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule drainage investigation work to be completed within 26 weeks. When the investigation has been completed, we will inform you of our findings and course of action.
Posted by North Northamptonshire Council at 15:38, Fri 28 November 2025
-
Questionnaire filled in by problem reporter
State changed to: Fixed
Posted anonymously at 11:16, Sun 21 December 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule drainage investigation work to be completed within 26 weeks. When the investigation has been completed, we will inform you of our findings and course of action.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysState changed to: Investigating
Posted by North Northamptonshire Council at 10:20, Wed 24 December 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 13:18, Wednesday 14 January 2026
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by North Northamptonshire Council at 09:24, Thursday 15 January 2026
-
Investigation: Completed (Defect Found), Defect Repair: Defect Found
State changed to: Investigating
Posted by North Northamptonshire Council at 13:37, Wednesday 21 January 2026