Deep potholes on the T juction by no 1 to 18 church view

Reported via mobile in the Potholes / Highway Condition category anonymously at 22:27, Fri 12 September 2025

Sent to North Northamptonshire Council less than a minute later. ref: 8159001.

These potholes have been here a long while and getting bigger which will cause an accident soon as cars/vans/lorries, try to dodge them. Please repair the whole corner before winter and them getting any bigger.

Updates

  • If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.

    Posted by North Northamptonshire Council at 22:27, Fri 12 September 2025

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by North Northamptonshire Council at 22:27, Fri 12 September 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 26 weeks. Please be assured that you will receive an update once repairs are concluded.

    Posted by North Northamptonshire Council at 13:28, Mon 15 September 2025

  • Area now has yellow painted circles around the potholes but nothing has been repaired yet.

    Posted anonymously at 22:43, Fri 10 October 2025
    Still open, via questionnaire

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue. A works order has been raised which you can follow on FMS-8159001-1 and add updates.

    Posted by North Northamptonshire Council at 09:35, Mon 13 October 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by North Northamptonshire Council at 11:26, Wed 3 December 2025

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by North Northamptonshire Council at 13:56, Fri 5 December 2025

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by North Northamptonshire Council at 14:45, Fri 5 December 2025