Fixed
Paving slab removed
Reported via desktop in the Slabs - Uneven / Damaged / Cracked category anonymously at 07:17, Wed 10 September 2025
Sent to North Northamptonshire Council less than a minute later. ref: 8144703.
The slab has been cracked / damaged for months - it has now broken into pieces and the pieces have been removed.
Updates
-
If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 07:17, Wed 10 September 2025
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 07:17, Wed 10 September 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 28 days. Please be assured that you will receive an update once repairs are concluded.
Posted by North Northamptonshire Council at 12:00, Sun 14 September 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 13:00, Mon 6 October 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by North Northamptonshire Council at 08:24, Wed 8 October 2025
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by North Northamptonshire Council at 09:29, Wed 8 October 2025
-
The paving slab has been removed and filled with tarmac that is poorly laid and not sealed at the edges- it looks more like a temporary fix than the temporary fix that was done.
State changed to: Open
Posted anonymously at 12:53, Wed 8 October 2025
-
The paving slab has been removed and filled with tarmac that is poorly laid and not sealed at the edges- it looks more like a temporary fix than the temporary fix that was done.
State changed to: Open
Posted anonymously at 15:39, Wed 8 October 2025
Still open, via questionnaire -
Investigation: Completed (No Action Necessary), Defect Repair: Work Completed - Thank you for your enquiry. We will monitor the condition as part of our routine highway inspection schedule. Should you notice the defect worsening, please inform us by raising a new enquiry.
State changed to: Fixed
Posted by North Northamptonshire Council at 14:13, Tue 14 October 2025
This report is now closed to updates from the public. You can make a new report in the same location.