Pot hole

Reported via mobile in the Potholes / Highway Condition category anonymously at 11:23, Tue 19 August 2025

Sent to North Northamptonshire Council less than a minute later. ref: 8045442.

A pot hole is expanding from a previous repair. About 20cm long and about 10cm deep.

Updates

  • If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.

    Posted by North Northamptonshire Council at 11:23, Tue 19 August 2025

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by North Northamptonshire Council at 11:23, Tue 19 August 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 28 days. Please be assured that you will receive an update once repairs are concluded.

    Posted by North Northamptonshire Council at 15:45, Fri 22 August 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by North Northamptonshire Council at 12:40, Fri 12 September 2025

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by North Northamptonshire Council at 11:12, Fri 19 September 2025

  • The pot hole has expanded/ deepened

    Posted anonymously at 14:39, Thu 27 November 2025

  • Investigation: Not Started (Defect Found), Defect Repair: To be Rescheduled

    State changed to: Investigating

    Posted by North Northamptonshire Council at 15:13, Tuesday 17 March 2026

  • Investigation: Not Started (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by North Northamptonshire Council at 09:26, Monday 23 March 2026

  • Investigation: Not Started (Defect Found), Defect Repair: To be Rescheduled

    State changed to: Investigating

    Posted by North Northamptonshire Council at 10:05, Thursday 26 March 2026

  • Investigation: Not Started (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by North Northamptonshire Council at 07:17, Friday 27 March 2026

  • Investigation: Not Started (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by North Northamptonshire Council at 13:08, Friday 27 March 2026

  • Investigation: Not Started (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by North Northamptonshire Council at 14:37, Friday 27 March 2026

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed - Thank you for your enquiry. We have attended the location and carried out a repair. Your enquiry will now be closed. If for any reason you believe we have not attended the correct defect, please inform us by raising a new enquiry.

    Posted by North Northamptonshire Council at 13:10, Friday 22 May 2026

This report is now closed to updates from the public. You can make a new report in the same location.