Zebra crossing markings faded

Reported via desktop in the Road Markings - Worn/Faded category anonymously at 14:02, Wed 2 July 2025

Sent to North Northamptonshire Council less than a minute later. ref: 7797604.

The zebra crossing by Nando's on the approach to Tesco is faded to the extent that cars are not recognising it and not stopping. Please can it be repainted.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by North Northamptonshire Council at 14:02, Wed 2 July 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started -
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by North Northamptonshire Council at 12:45, Tue 8 July 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by North Northamptonshire Council at 10:35, Fri 18 July 2025

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by North Northamptonshire Council at 21:42, Fri 12 December 2025

  • Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled

    State changed to: Investigating

    Posted by North Northamptonshire Council at 16:23, Mon 15 December 2025

  • Zebra crossing on carina way by tesco garage. I have had several bear misses when using due to lines not being visable and drivers not stopping. Today i was in middle of tuad when driver failed to stop. Lines need repainting for safety

    Posted anonymously at 12:02, Monday 19 January 2026

  • Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled - Thank you for your enquiry. We will schedule a repair to be completed within 180 days (26 weeks), however we are currently operating for completion to be within 90 days. Please be assured that you will receive an update once repairs are concluded.

    Posted by North Northamptonshire Council at 13:10, Monday 26 January 2026

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by North Northamptonshire Council at 09:09, Thursday 19 March 2026

  • Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled

    State changed to: Investigating

    Posted by North Northamptonshire Council at 22:12, Thursday 2 April 2026

Only the original reporter may leave updates. If you made the original report please log in to leave an update.