Drain not taking water

Reported via desktop in the Blocked/Damaged category anonymously at 11:16, Fri 6 June 2025

Sent to North Northamptonshire Council less than a minute later. ref: 7670537.

Chamber full to top of grid, water flowing past down road

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.

    Posted by North Northamptonshire Council at 11:16, Fri 6 June 2025

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by North Northamptonshire Council at 11:16, Fri 6 June 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 26 weeks. Please be assured that you will receive an update once repairs are concluded.

    Posted by North Northamptonshire Council at 14:21, Fri 13 June 2025

  • Definitely blocked

    Posted anonymously at 19:54, Fri 14 November 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 180 days (26 weeks), this is expected to be completed by 12/12/2025. Please be assured that you will receive an update once repairs are concluded.

    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by North Northamptonshire Council at 13:49, Fri 21 November 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by North Northamptonshire Council at 10:51, Monday 26 January 2026

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by North Northamptonshire Council at 08:59, Thursday