Reported via desktop in the Potholes / Highway Condition category anonymously at 08:58, Saturday 8 February 2025
Sent to North Northamptonshire Council less than a minute later. ref: 7103562.
Large pothole/road erosion bottom of dip near the river,it is now very dangerous and will cause an accident f not repaired.Also there are multiple potholes on the side of road between Desborough and Rushton
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 08:58, Saturday 8 February 2025
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 08:58, Saturday 8 February 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started -
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by North Northamptonshire Council at 14:53, Thursday 13 February 2025
-
Reported problem has not been fixed and the whole road from Rushton to Desborough is a disgrace
Posted anonymously at 14:06, Saturday 8 March 2025
Still open, via questionnaire -
Investigation: Not Started (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 10:15, Monday 10 March 2025
-
Investigation: Completed (Scheduled Maintenance), Defect Repair: Scheduled - Thank you for your enquiry. We can confirm that we have been made aware of this issue. A works order has been raised which you can follow on 7103562 and add updates. The expected completion date for these works will be 13 3 25
Posted by North Northamptonshire Council at 20:01, Monday 10 March 2025
-
Investigation: Completed (Scheduled Maintenance), Defect Repair: Ongoing
State changed to: In progress
Posted by North Northamptonshire Council at 12:06, Wednesday 12 March 2025
-
Investigation: Completed (Scheduled Maintenance), Defect Repair: Work Completed
State changed to: Fixed
Posted by North Northamptonshire Council at 14:08, Wednesday 12 March 2025