3 large potholes and damaged kerb

Reported via mobile in the Potholes / Highway Condition category by David H Woods at 15:35, Tuesday 28 January 2025

Sent to North Northamptonshire Council less than a minute later. ref: 7047429.

These potholes have developed over this winter and getting larger each day. Kerb has also been damaged today caused by large vehicles turning round. Located in exit from Alledge Drive Into Thrapston Road Woodford

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.

    Posted by North Northamptonshire Council at 15:35, Tuesday 28 January 2025

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by North Northamptonshire Council at 15:35, Tuesday 28 January 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We will schedule a repair to be completed within 28 days. Please be assured that you will receive an update once repairs are concluded.

    Posted by North Northamptonshire Council at 18:13, Sunday 2 February 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by North Northamptonshire Council at 07:37, Wednesday 26 February 2025

  • Potholes getting larger, looks a temporary fill was done when kerb was replaced

    Posted by David H Woods at 08:46, Wednesday 26 February 2025
    Still open, via questionnaire

  • Investigation: Not Started (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by North Northamptonshire Council at 09:41, Thursday 27 February 2025

  • Investigation: Not Started (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by North Northamptonshire Council at 10:18, Thursday 27 February 2025

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed - Thank you for your enquiry. We can confirm that we have been made aware of this issue and a works order has been raised on a routine safety inspection. The expected completion date for these works will be 31/07/25

    Posted by North Northamptonshire Council at 18:18, Friday 28 February 2025

This report is now closed to updates from the public. You can make a new report in the same location.