Fixed
General road condition
Reported via mobile in the Potholes / Highway Condition category anonymously at 07:17, Fri 11 October 2024
Sent to North Northamptonshire Council less than a minute later. ref: 6577935.
Please inspect the full length of this road for pot holes, there are numerous pot holes along it, to many for me to sit and report everyone.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 07:17, Fri 11 October 2024
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 07:17, Fri 11 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the NNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 14.3 days.
Posted by North Northamptonshire Council at 08:15, Fri 18 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 08:45, Tue 22 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by North Northamptonshire Council at 10:45, Thu 24 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Temporary Repair Completed - A permanent repair will be carried out in the next 28 days.
Posted by North Northamptonshire Council at 12:38, Thu 24 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 07:06, Thu 31 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by North Northamptonshire Council at 09:05, Mon 4 November 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by North Northamptonshire Council at 12:39, Mon 18 November 2024
This report is now closed to updates from the public. You can make a new report in the same location.