Fixed
Severe natural spring leak
Reported via desktop in the Obstruction (Not Vegetation) category by Mrs Suzanne M Grant at 12:18, Wed 28 August 2024
Sent to North Northamptonshire Council less than a minute later. ref: 6407258.
What3words location = brass.types.renovated Severe natural spring leak in London Road which has made the path unusable and dangerous
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 12:18, Wed 28 August 2024
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 12:18, Wed 28 August 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the NNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 26.7 days.
Posted by North Northamptonshire Council at 13:05, Mon 2 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 12:29, Thu 12 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by North Northamptonshire Council at 10:44, Mon 16 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by North Northamptonshire Council at 09:49, Fri 20 September 2024
-
Still open, via questionnaire, 14:03, Wed 25 September 2024
-
The severe leak has not been resolved (6407258) and remains in the same state as when reported, so please can you readdress and the work has not been completed. Thank you.
State changed to: Open
Posted by Mrs Suzanne M Grant at 12:24, Wed 30 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the NNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 26.7 days.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysState changed to: Fixed
Posted by North Northamptonshire Council at 15:25, Wed 20 November 2024
This report is now closed to updates from the public. You can make a new report in the same location.