In progress
Blocked drains
Reported via mobile in the Blocked/Damaged category by Craig Blacha at 09:35, Tue 27 August 2024
Sent to North Northamptonshire Council less than a minute later. ref: 6401586.
Approximately 4 blocked drains along Ditchford Lane Rushden before the bridge as you just come off the roundabout.
The road is partially closed but would be open to permanently repair the defect.
Blocked drains fits the matrix of general defect in the Highways Safety Inspection Manual.
This road is medium on the severity scale as as is used as a link road but currently due to bridge repairs is partially closed.
As per the manual this should be suitable for a P3 repair.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 09:35, Tue 27 August 2024
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 09:35, Tue 27 August 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the NNC Highways Inspection Manual, the flooding has been assessed and requires a Priority 4 response. We will schedule drainage investigation work to be completed within 26 weeks. When the investigation has been completed, we will inform you of our findings and course of action. Our current average response time for a Priority 4 is 119.6 days.
Posted by North Northamptonshire Council at 09:25, Sun 1 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 11:07, Thu 12 September 2024
-
Still open, via questionnaire, 11:35, Tue 24 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by North Northamptonshire Council at 13:42, Fri 18 October 2024
Only the original reporter may leave updates. If you made the original report please log in to leave an update.