Investigating
Potholes that have been marked for repairs for some months still not repaired.
Reported via Android in the Potholes / Highway Condition category anonymously at 06:56, Thu 1 August 2024
Sent to North Northamptonshire Council less than a minute later. ref: 6301313.
Long standing potholes for repair still not rectified.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 06:56, Thu 1 August 2024
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 06:56, Thu 1 August 2024
-
Investigation: Completed (Defect Found) - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the NNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 119.6 days.
Posted by North Northamptonshire Council at 13:57, Tue 6 August 2024
-
Not yet repaired.
Posted anonymously at 12:04, Thu 29 August 2024
Still open, via questionnaire -
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by North Northamptonshire Council at 12:04, Thu 29 August 2024
-
Investigation: Completed (Defect Found) - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the NNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 119.6 days.
Posted by North Northamptonshire Council at 18:08, Mon 2 September 2024
-
Questionnaire filled in by problem reporter
State changed to: Fixed
Posted anonymously at 13:04, Thu 26 September 2024
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 13:04, Thu 26 September 2024
-
Investigation: Completed (Defect Found) - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the NNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 119.6 days.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport