Pothole as you go past Warmington garage towards Oundle been there a long while still not fixed

Reported via mobile in the Potholes / Highway Condition category anonymously at 21:51, Thu 23 May 2024

Sent to North Northamptonshire Council less than a minute later. ref: 6013823.

Pothole as you come from Warmington roundaboutt past garage before Luton turn

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.

    Posted by North Northamptonshire Council at 21:51, Thu 23 May 2024

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by North Northamptonshire Council at 21:51, Thu 23 May 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 28 days.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by North Northamptonshire Council at 09:10, Fri 31 May 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by North Northamptonshire Council at 14:55, Thu 6 June 2024

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by North Northamptonshire Council at 11:37, Mon 17 June 2024

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by North Northamptonshire Council at 13:21, Mon 17 June 2024

This report is now closed to updates from the public. You can make a new report in the same location.