Blocked drain
Reported via mobile in the Blocked/Damaged category anonymously at 14:03, Thu 4 April 2024
Sent to North Northamptonshire Council less than a minute later. ref: 5806676.
This drain is totally blocked. It may not be deemed to be a flood risk as it is at the top of the street, however in heavy storms it takes no rainwater, not helping those properties at the end of Salisbury st.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are an emergency (such as flooding, highway obstructions fallen trees), please call 0300 126 3000, Monday to Friday (9.00 to 17.00). Outside these hours, please call 01604 651074.
Posted by North Northamptonshire Council at 14:03, Thu 4 April 2024
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by North Northamptonshire Council at 14:03, Thu 4 April 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Having inspected the gully here, we can confirm work is scheduled within the next 28 days on the gully here. This work will involve cleaning out and jetting the gully. We will endeavour to complete it as quickly as possible. You will receive further updates once it has been completed. If a flooding emergency occurs, call 0300 126 3000 for North Northamptonshire Council between 9.00 and 17.00. Outside of these hours, please ring 01604 651074.
For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @nnchighwaysPosted by North Northamptonshire Council at 16:03, Wed 10 April 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by North Northamptonshire Council at 10:11, Tue 16 April 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by North Northamptonshire Council at 12:37, Tue 16 April 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by North Northamptonshire Council at 13:04, Tue 16 April 2024
-
Still open, via questionnaire, 16:59, Thu 2 May 2024
Only the original reporter may leave updates. If you made the original report please log in to leave an update.